Sr. No. Name of Work Place and Location Tendered Amount Rs. In Lacs Cost on Completion Rs. In Lacs Original Time limit in month Extended time limit in month Time taken in month to complete the work Reason for delay in completion Remarks
1 Moj Irri. Scheme Dist: Rajkot 203.48 226.71 11 0 7 Completed in time Work completed
2 Suvi Fatehgadh M.I. Sc Dist: Bhuj 186.86 221.27 12 0 12 Completed in time Work completed
3 Lunva, Aadhoi-I and II M. I. S. Dist: Bhuj 70.48 45.75 12 8 20 N/A of line Work completed
4 Dhrang, Chunari…M.I.S Dist: Bhuj 206.97 190 12 3 15 N/A of line Work completed
5 Baukha, Fulay….M. I. S Dist: Bhuj 198.04 160.64 12 0 12 Completed in time Work completed
6 Surkhan, Devalia…M.I.S. Dist: Bhuj 111.74 116.53 12 0 12 Completed in time Work completed
7 Shivlakha M. I. Schme Dist: Bhuj 52.49 36.98 9 18 27 N/A of line Work completed
8 Ludva M. I. Scheme Dist: Bhuj 48.92 48.92 9 0 9 Completed in time Work completed
9 Aladar and Paniyadhar 6G6(I) Dist: Bharuch 736.48 734.76 36 8 44 Due to land acquiction Work completed
10 Dhrangadhra Br. Canal Acquduct Dist: Surendranagar 1330.92 1565.25 18 16 34 Due to forest land acquesition Work completed
11 Mota Layja M. I. Sch. Dist: Bhuj 352.31 474.43 12 3 15 Approval of foundation Work completed
12 Navagam (Manaba) Bandhara Dist: Bhuj 913.9 966.38 24 0 24 Completed in time Work completed
13 SyphoN/And Escape in S.B.Canal Dist: Surendranagar 1703.75 1197.18 11 3 14 Due to heavy rain work could not started in river porson Work completed
14 Visalia Bandhara Dist: Amereli 672.27 674.23 18 0 19 N/A of line due to land aquition Work completed
15 Ukai Left Bank High Level Canal (Lining) Dist: Tapi 422.04 410.19 15 0 15 Completed in time Work completed
16 Ozat-II Irrigation Scheme L. B. M. Canal Dist: Junagadh 262.62 259.78 11 5 16 Due to land acquiction Work completed
17 Ukai Left Bank High Level Canal (Structure) Dist: Tapi 355.29 360.63 15 0 15 Completed in time Work completed (final Bill under process)
18 Super Passage of SSNNL (Structure work) Dist: Banas 2202.27 1998.5 18 0 16 Completed in time Work completed (final Bill under process)
19 Una Big Check Dam Dist: Junagadh 79.31 74.1 11 5 16 Due to water flow in river Work completed (final Bill under process)